October 8, 2026
Liberty State Park had a busy September 2026. The state cut the ribbon on a $51.1 million ferry terminal. Liberty Science Center broke ground on a $40 million expansion. Caven Point Beach reopened for the colder months. The finished work mostly serves people crossing the harbor to the Statue of Liberty and Ellis Island. The projects closest to daily Jersey City life don't have opening dates yet. Those are the fields, the picnic grove and the trails through the fenced interior.
Here's what is done, what is underway, and what is still on paper as of the last week of September.
On September 22, 2026, the New Jersey Department of Transportation and the Department of Environmental Protection cut the ribbon on the expanded Liberty State Park Ferry Terminal. The $51.1 million project rebuilt the historic Central Railroad of New Jersey ferry terminal, which had sat largely unused since the park was established in 1976. A sunken barge was replaced with a new pier structure and barge. The old barge got a second life as an artificial reef off the Jersey Shore. Federal funds covered about $41 million, roughly 80 percent of the cost.
The ceremony doubled as the annual Great Boatlift commemoration. About 30 vessels took part, honoring the maritime evacuation of September 11, 2001. DEP Commissioner Ed Potosnak called the terminal "New Jersey's only access point for visitors traveling to the Statue of Liberty and Ellis Island."
That describes who the terminal is for. Statue City Cruises still sends passengers to the ticket office inside the historic CRRNJ Terminal, then through screening to departures from the Lot 8 side. Parking is $7 per vehicle. If you mostly use the park for a run along the water or a picnic near the Empty Sky memorial, you will see the terminal change. You may not use it much.
Two weeks before the ferry ceremony, on September 10, Liberty Science Center broke ground on Project Supernova. The state backed the plan with a $39.6 million tax credit over five years through its new Cultural Arts Facilities Expansion program.
The plans lean hard toward outdoor space:
Inside, River Rising will replace the Our Hudson Home exhibit, and the former Skyscraper! space will become a larger premium-exhibit gallery. The planetarium projection and Science on a Sphere systems are getting upgrades, and Dino Dig and Wild About Animals are being refreshed. CEO Paul Hoffman described the goal as turning the center into "an all-weather campus."
There is no completion date. Jersey Digs reported on September 28 that no estimated timeline had been announced. For now, a visit works as usual. The center's directions page still lists the 750-space state-owned lot at $7 per car and the Phillip Street drop-off for visitors with special needs. It doesn't mention any construction detours.
The space linking the ferry terminal to the rest of the waterfront is still a work zone. Terminal Plaza sits at the end of Audrey Zapp Drive and connects the Empty Sky memorial and the CRRNJ Terminal to the Hudson River Waterfront Walkway. On September 23, DEP's revitalization page said: "Construction is underway, with the plaza expected to reopen to visitors later in 2026."
Right behind it, the Historic Train Shed is being restored in phases. Phase one covers 60,000 square feet on the east side, next to the terminal building, and will become event and gathering space with seating. In July, a roundup of permits affecting the walkway noted that DEP had applied to rebuild part of the shed. No opening date has been published for phase one.
One change has already happened. DEP says the free park shuttle, now in its third year, ran on weekends, holidays and event days through September 6, 2026. For the rest of fall, getting between parking lots is up to you.
| Project | Status | Latest official word |
|---|---|---|
| Ferry Terminal | Open | Ribbon cutting September 22, 2026 |
| Caven Point Beach | Open for fall and winter | Reopened September 26, 2026 |
| Project Supernova | Under construction | Broke ground September 10, no completion date |
| Terminal Plaza | Under construction | "Later in 2026" |
| Train Shed, phase one | In early work | No opening date |
| Marina Green | No new public update | January 2026 release |
| Park interior | Fenced | Construction start targeted for summer 2027 |
| Liberty Landing Marina lease | Unresolved | Latest report March 2026 |
In January 2026, DEP named three priority construction projects: Terminal Plaza, Marina Green and the first phase of the Train Shed. It said nearly $54 million was set aside for construction and that openings were expected "in the second half of 2026 and into 2027."
Of the three, Marina Green would change an ordinary weekend the most. The eight-acre plan includes athletic fields, a flexible lawn, play space, a shade pavilion, a picnic grove and walking paths. We found no construction update or opening notice for Marina Green between April and September.
The interior is on a longer timeline. More than 230 acres in the middle of the park have been fenced off for decades because of industrial pollution. DEP and the U.S. Army Corps of Engineers began the first cleanup in October 2023. The restoration plan calls for wetlands, overlooks, a 5.6-mile trail network and a future Southern Athletics Hub with fields and courts.
DEP's current restoration schedule runs in three steps:
DEP hasn't published an opening date for the trails. When ground broke in 2023, TAPinto quoted an Army Corps target of finishing the interior work "by next summer." DEP's 2026 schedule has replaced that target.
Liberty Landing Marina has 250 slips, transient dockage, dry storage, fuel, maintenance and two restaurants. A proposed lease with Suntex would allow a 500-boat dry-rack building up to 70 feet tall on about 2.3 acres, plus up to $30 million in state bulkhead funding.
The State House Commission approved the lease 5 to 2 on January 15. On January 30, Hudson County View reported that the lease was still unsigned. Environmental groups appealed on February 26. A March 10 report said the project "appears to be at a standstill." We found no later report of a signing, a cancellation or a court ruling. For now it is a possible future change, not something under construction.
The reopening most useful to residents this fall didn't take a construction contract. NJDEP marked National Public Lands Day on Saturday, September 26, by reopening Caven Point Beach for the fall and winter seasons. The bulletin opened with "Who else has been waiting all summer for Caven Point Beach to re-open?" The event started with a walk from Lot 1 at 300 Morris Pesin Drive. The route is 2.5 miles round trip on flat ground, and parking is free. The day included a naturalist's talk on "What lives in this estuary?", watercolor and mosaic sessions with the Educational Arts Team, native plants from the Hudson County chapter of the NJ Native Plant Society, and books from the Jersey City Free Public Library. Snacks were sponsored by the Friends of Liberty State Park.
October's calendar fills in the rest. DEP's nature programs require advance registration.
At Amy DeAngelo Real Estate, we follow projects like Terminal Plaza and Marina Green because they shape what owning a home near the park feels like, years before they reach a listing description. If you live near Liberty State Park and want to know how this round of construction might show up in your home's value, Amy DeAngelo Real Estate can walk you through it with a free home valuation.
Stay up to date on the latest real estate trends.
Experience a real estate partnership built on trust, expertise, and genuine care. Amy brings a lifelong understanding of what “home” truly means to every client and every decision.